Foreign project - FAT factory undergoing testing
For FAT Factory Acceptance Test, as a part of the ISO file system, the factory test documents are generally conducted according to the IEC standard factory test items, including special requirements for customer requirements, particularly strengthening the secondary system function inspection.

Standard format files generally include the following content:
Scope Scope The Mandatory Routine tests (refer clause 7 of IEC 62271-1 and IEC 62271-200) are as follows
The mandatory routine tests are as follows (refer to Chapter 7 of IEC 62271-1 and IEC 62271-200) Preparation before Test
Prepare EHS requirements before testing
safety requirements
List of inspection Item, standard and testing equipment
List of testing items, standards, and testing equipment
FAT test procedure FAT
Dielectric test on the main circuit
Measurement of the resistance of the main circuit through dielectric testing
Design and visual checks for measuring the resistance of the main circuit
Mechanical operation tests for design and appearance inspection
Mechanical operation testing Tests on Auxiliary and control circuits & Test of auxiliary electrical devices(interlocks)
Auxiliary and control circuit testing and auxiliary electrical device testing (lockout) Bus bar inspection
Busbar inspection Protection level inspection
Protection level inspection
Foreign projects will pay attention to the performance parameters of components, such as the mechanical performance of circuit breakers, opening and closing time, as well as the phase sequence, inflection point voltage, and other parameters of current transformers and voltage transformers. The parameters will be verified through a current injection test, and the system function will be verified, such as the parameter setting verification of microcomputer protection devices and the accuracy of actions.

There are also requirements for surface spraying, thickness, color difference, copper bar material inspection, conductivity measurement, and silver plating thickness measurement. These require spot checks and confirmation of incoming inspection reports. If inconsistencies are found, more items may need to be inspected, which may affect integrity.
FAT Test report FAT
The test report FAT report is officially archived and retained by the customer.
It is recommended that the manufacturer first complete the testing and verification of key factory projects on their own, such as power frequency withstand voltage, appearance inspection (surface spraying, label identification), circuit breaker rocking in and out, grounding switch operation and interlocking verification, to ensure that everything is foolproof and avoid problems in front of customers, which may affect the company's image in production management, quality control and other aspects, causing a lack of trust and inability to obtain subsequent projects.
~END
Recently Posted
-
Medium voltage MCC motor control cabinet
September 17, 2026Regarding the arcing of medium voltage FC switchgear, F-C refers to the combination of contactor and fuse. FC is mainly used for motor protection, and the contactor has a long electrical life of at least 300000 times, suitable for frequent operation. Fuses are used for overload protection. FC is widely used in steel mills, chemical plants, coal-fired power plants, ships, and offshore oil platforms. In these situations, the shRead More -
Guidelines for Calculation and Design of Low Voltage Switchgear
September 16, 2026IEC 61439 replaces IEC60439 and introduces the principle of verifying switchgear. These replace the existing Type Test Assembly (T
Read More -
Temperature rise of 40.5kV 3150A environmentally friendly gas insulated switchgear
September 15, 2026Environmentally friendly gas insulated switchgear uses environmentally friendly gases such as nitrogen and dry air to replace sulf
Read More -
Connection of copper bars in switchgear
September 14, 2026Switchgear is not simply using copper bars to connect components according to a system diagram, which involves complex system engi
Read More